Analisis Network Planning dengan Critical Path Method (CPM) Dalam Rangka Efisiensi Waktu dan Biaya Proyek Pembangunan Rumah Minimalis (Studi Kasus: Property Group Medan)
DOI:
https://doi.org/10.30865/json.v2i1.2459Keywords:
Schedule, Activities, Critical Pathways, Cost, CPMAbstract
The development of science and technology in the field of computers is currently so fast, along with many new discoveries that are useful in developing this technology. This greatly affects the performance of each agency and company in dealing with any problems that arise in data processing. Analysis of the application of time management in home construction construction projects, using the Microsoft Project 2007 application, is very helpful for contractors in managing home construction projects, starting from making project plans, allocating resources, planning construction project costs, making project movement plans and evaluating projects. in accordance with the provisions for completing the study in the Information Systems undergraduate program which must make a thesis.References
Nurhayati, “Manajemen Proyekâ€, Graha Ilmu, Yogyakarta, 2010
Kusrianto Adi, “Panduan Lengkap memakai Microsoft office projectâ€, PT Elex Media Komputindo, Jakarta, 2012
Abrar Husen, “Manajemen Proyek Network Planningâ€, Graha Ilmu, Yogyakarta, 2010
Sugianto Mikael, “Pengelolaan Proyek Kontruksi dengan Microsoft Project 2010†CV. Andi Offset, 2012
Ervianto Wulfram, “Teori Aplikasi Manajemen proyek Kontruksiâ€, CV. Andi Offset, Yogyakarta, Edisi 1, 2005
http://www. Perhitungan waktu Pert.com, diakses pada 21 Mei 2014
http://www. Metode pert jalur kritis.com diakses pada 21 Mei 2014
http://www. Metode Cpm waktu kritis, diakses pada 21 Mei 2014
http//www. elib.unikom.ac.id, diakses pada 21 Mei 2014